In the May 2022 edition of the CEO Update, we provide an outline of some key activities here at Perth Markets including an update on the Site Masterplan, an outline of a site valuation and establishme
New Gas Installation
Market West is in the process of relocating the existing gas pumping station under the Eastern Buyers Bays out into the area on the corner of the eastern roadway and the southeast end of the buyer’s b
CTA Roof Works
Workers are replacing significant portions of the existing perspex sheeting in the CTA. The existing sheeting was well past its useful life and presented as a safety hazard which needed removal and re
Waste Management
Cleanaway has been appointed the site waste transport provider commencing July 1, 2022, for a 5-year term. The pricing for the waste management transport service does not change between the outgoing a
Road Resurfacing 2022
The site has programmed major road works scheduled to take place in mid-June 2022. These capital works are targeted at areas where the existing bitumen is close to end of life. It is envisaged that th