Please be advised of planned Phase 1 – Road Resurfacing works to the Eastern component of the ring road (shaded green on the attached drawing)

These works are due to commence at 10am Tuesday 14 June and are due for completion by  3pm on Saturday 18 June

A Traffic Management Plan will be implemented as detailed on the drawing.

Due to the nature of the works, there will be NO ACCESS within the work area during the duration of the Project.

A detailed schedule of works is as follows:

  • 10am Tuesday 14 June
    • Implement Traffic Management and commence Profiling works
  • Wednesday June 15
    • Continue Profiling works
  • Thursday 16 June
    • Seal road in preparation for Asphalting
  • Friday 17 and Saturday 18 June
    • Conduct Asphalting

Should you have any questions, please contact our Facilities Manager, Dilip Henderson at dhenderson@perthmarket.com.au